What a South African construction site needs before and during work: permit, H&S plan and file, fencing, toilets, showers, storage, fire and first aid.
Last reviewed · Guidance, not legal advice
"Site establishment" is not a term the law defines. It is the work of getting a construction site ready: the paperwork, the fence, the facilities for workers, the storage areas, the fire equipment and the temporary electrics. The Construction Regulations, 2014 set out what must be there. This guide goes through it in the order a site is usually set up.
Draft replacement regulations, titled Construction Regulations, 2024, were published for comment in March 2025 and had not been finalised when this guide was reviewed.[4] This guide follows the Construction Regulations, 2014.
Before anyone starts work
Permit or notification. A client must apply for a construction work permit at least 30 days before work starts if the work will exceed 180 days, involve more than 1800 person days, or be worth R13 million or more or CIDB grade 6 (regulation 3(1)). The site specific number on the permit must be displayed conspicuously at the main entrance (regulation 3(4)). Other work that includes excavation, work at height with a risk of falling, demolition or explosives must be notified at least 7 days before it starts (regulation 4(1)).[1]
The plan and the file. The principal contractor must provide a site specific health and safety plan, based on the client’s specification, and apply it for the duration of the work (regulation 7(1)(a)). The client must approve that plan (regulation 5(1)(l)). The principal contractor must open and keep a health and safety file on site (regulation 7(1)(b)), and each contractor must do the same for its own work (regulation 7(2)(b)).[1]
Induction and fitness. No contractor may let anyone enter the site unless they have had induction training on the hazards on the site at the time (regulation 7(5)). Visitors must also be inducted and given the personal protective equipment they need (regulation 7(6)), and the induction records must be kept on site (regulation 7(7)). Every employee needs a valid medical certificate of fitness for the construction work they do (regulation 7(8)).[1]
Who pays for it
Facilities and safety measures cost money, so the regulations deal with that at tender stage. The client must make sure that principal contractors tendering for the work have made adequate provision for the cost of health and safety measures (regulation 5(1)(g)). The principal contractor must do the same for contractors tendering to it (regulation 7(1)(c)(ii)).[1]
Fencing, access and housekeeping
A site in a built up area next to a public way must be suitably and sufficiently fenced off, with controlled access points to keep unauthorised people out (regulation 27(f)).[1]
Regulation 27 also requires housekeeping to be implemented continuously, including:[1]
- proper storage of materials and equipment (27(a))
- removing scrap, waste and debris at appropriate intervals (27(b))
- not placing materials where they block access to and from workplaces and passageways (27(c))
- removing materials that are no longer needed (27(d))
- a catch platform or net, or fencing off the danger area, where people work or pass under work being done above (27(g))
Regulations 27 and 29 apply in addition to the Environmental Regulations for Workplaces, 1987. For workplaces generally, housekeeping is now in regulation 13H of the General Safety Regulations and fire precautions and means of escape in regulation 13J (GN 5954, March 2025),[5] and the Environmental Regulations for Workplaces, 1987 were repealed in September 2026, 18 months after the Physical Agents Regulations were published (regulation 21 of those Regulations).[6]
Toilets, showers, changing and eating areas
Regulation 30(1) requires the contractor to provide, at or within reasonable access of every construction site, clean, hygienic and maintained:[1]
- shower facilities, after consulting the employees or their representatives, or at least one shower for every 15 persons (30(1)(a))
- at least one sanitary facility for each sex and for every 30 workers (30(1)(b))
- changing facilities for each sex (30(1)(c))
- sheltered eating areas (30(1)(d))
Where workers are far from home and there is no adequate transport or other suitable accommodation, the contractor must provide reasonable and suitable living accommodation (regulation 30(2)).[1]
Regulation 30 applies in addition to the Facilities Regulations, 2004. Those regulations require every employer to:[2]
- provide toilet paper and soap or a similar cleansing agent free of charge (regulation 2(3)(a) and (d))
- make an adequate supply of drinking water available, and clearly mark taps and pipes that are not fit for drinking (regulation 7)
- provide each employee, other than office workers, with a facility to keep clothes and personal items safely (regulation 3(1))
- keep every prescribed room and facility clean, hygienic, safe, whole, leak free and in good repair (regulation 9)
Storage and stacking
The contractor must appoint a competent person in writing to supervise all stacking and storage on the site, provide adequate storage areas, demarcate them, and keep them neat and under control (regulation 28).[1]
Flammable liquids need their own care under regulation 25: they must be used and stored without causing a fire or explosion hazard, with effective ventilation; nobody may smoke where they are used or stored, with notices at every entrance; and efficient fire fighting equipment must be installed around the store. Only one day’s quantity may be taken out of the store, containers must be kept closed, and other flammable material such as rags and paper must not be stored with them.[1]
Fire precautions
Regulation 29 requires, among other things:[1]
- suitable and sufficient fire extinguishing equipment at strategic locations, kept in good working order (29(g))
- that equipment inspected by a competent person appointed in writing, as the manufacturer indicates (29(h))
- enough workers trained to use it (29(i))
- escape routes signposted where appropriate and kept clear (29(j) and (k))
- an effective evacuation plan that gets people out quickly, accounts for everyone and shuts down plant and processes (29(l))
- a siren that is sounded in the event of a fire (29(m))
Temporary electrical installations
In addition to the electrical regulations, the contractor must (regulation 24):[1]
- find out, before work starts and as it goes on, whether there are electrical cables or apparatus under, over or on the site, and guard against them (24(a))
- put the control of all temporary electrical installations in the hands of a competent person appointed in writing (24(c))
- have every temporary installation inspected at least once a week by a competent person, with the findings recorded in a register kept on site (24(d))
- have the operator or user inspect electrical machinery every day before use, with a checklist, and record it in a register on site (24(e))
First aid
Where more than 10 employees work at a workplace, the employer must make sure that for every group of up to 50 employees at least one person with a valid first aid certificate of competency, from an organisation approved by the Chief Inspector, is readily available during normal working hours (General Safety Regulations, regulation 3(4), as substituted in December 2025).[3]
Keeping it in order
The facilities are only half of it: the registers, appointments and inspections have to be kept up for the life of the site. ProComply keeps each site’s appointments, inspection checklists and contractor documents together, so the health and safety file is complete when an inspector or client asks for it.
Sources
- [1]Construction Regulations, 2014 (GNR 84, Government Gazette 37305, 7 February 2014) (gov.za, accessed 25 November 2026)
- [2]Facilities Regulations, 2004 (GNR 924, Government Gazette 26636, 3 August 2004) (gov.za, accessed 25 November 2026)
- [3]Amendment of the General Safety Regulations, regulation 3(4) first aid (GN 6907, Government Gazette 53783, 5 December 2025) (gov.za, accessed 25 November 2026)
- [4]Construction Regulations, 2024: invitation of public comments on the draft (GN 5983, Government Gazette 52267, 12 March 2025) (labour.gov.za, accessed 25 November 2026)
- [5]General Safety Regulations, 2025: regulations 13H and 13J (GN 5954, Government Gazette 52226, 6 March 2025) (gov.za, accessed 25 November 2026)
- [6]Physical Agents Regulations, 2024 (GN 5952, Government Gazette 52226, 6 March 2025) (gov.za, accessed 25 November 2026)